According to the PMBOK the activity attributes are "multiple attributes associated with each schedule activity that can be included within the activity list. Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions."

The activity list and the related activity attributes are created by (outputs from) the define activities process, and both are inputs to the sequence activities, estimate activity durations, develop schedule, and estimate activity resources processes. ‎