Bottom-up estimating is a technique that can be used to estimate activity resources or estimate costs. The amounts for the decomposed elements are calculated and summed to estimate the amount for the larger unit.

See section 6.4.2.3 of the PMBOK 5th edition for more about bottom-up estimating of the activity resources and 7.2.2.4 for bottom-up estimating of the costs.

Related: estimate to complete