FANDOM


168th of 2nd 365- A choice. Which translation to continue reading?

Questions?

The following are practice questions for the PMP and CAPM exams. The answers given are from the cited sources; their correctness is not guaranteed.

Practice QuestionEdit

See answers at the end of this article.
1. Which amongst the following would not be relevant for creating the quality management plan?

A. Checklists
B. Organizational quality policy
C. Project scope baseline
D. Schedule baseline [1]

2. A single-source seller means what?

A. There is only one qualified seller
B. There is only one seller the company wants to do business with
C. There is a seller that can provide all aspects of the project procurement needs
D. There is only one seller in the market [2]

3. Gordon is currently developing his project’s stakeholder management strategy. All enterprise environmental factors should be considered during this process. Which of the following enterprise environmental factors should be paid special attention during this process?

A. Project templates
B. Commercial databases
C. Lessons learned from past similar projects
D. The organization's culture and structure[3]

4. If a stakeholder has any questions about project deliverables, as the PM, you should direct him to the:

a) WBS
b) Project plan
c) Preliminary Scope statement
d) None of the above [4]

5. You are the project manager for a high visibility project. The margin on this project is low, and it is extremely important that the cost estimates for the work on the project be accurate. While reviewing the cost estimates for this project you notice that one of the cost estimates for an element in the WBS is 10% higher than two previous projects for very similar work. What should you do?

a. Accept the estimate because you trust all of the people on your project team, and they are responsible for estimates
b. Reduce the estimate and add the additional budget to the management reserve
c. Ask the person responsible for the estimate to explain the difference and bring supporting information to you
d. Reduce the estimate and add the additional budget to the contingency reserve [5]

spacers before answers


Answers to practice questionsEdit

1. A. Checklists.
2. B. There is only one seller the company wants to do business with.
3. D. The organization's culture and structure.
The lessons learned and the project templates are not enterprise environmental factors, these are organizational process assets. The commercial databases can provide very limited information to develop the stakeholder management plan. During the Plan Stakeholder Management process, the organization’s culture and structure are of particular importance. [PMBOK 5th edition, Page 401][6]
4. A. WBS.
5. C. Ask the person responsible for the estimate to explain the difference and bring supporting information to you.

ReferencesEdit

  1. Udemy blog PMP Exam Questions: 25 Q&As for Exam Day by Brittani Sponaugle on April 3, 2014
  2. Udemy blog PMP Exam Questions: 25 Q&As for Exam Day by Brittani Sponaugle on April 3, 2014
  3. PMP DEN PMP Exam Questions 11 – Project Stakeholder Management
  4. 206 Free practice questions for PMP® exam
  5. PMP Bank PMP Questions, question 2.
  6. PMP DEN PMP Exam Questions 11 – Project Stakeholder Management

External linksEdit

Links to sites with more practice questions:

Ad blocker interference detected!


Wikia is a free-to-use site that makes money from advertising. We have a modified experience for viewers using ad blockers

Wikia is not accessible if you’ve made further modifications. Remove the custom ad blocker rule(s) and the page will load as expected.