Perform integrated change control is the PMI process that handles change requests -- approving or denying them, tracking them in the change log, and updating other project documentation to reflect any approved changes.

Related: change control board, change control board, scope creep

Change management may overlap with change control, but in general change control refers to changes to the project, such as scope changes, and change management techniques usually deal with organizational changes.

According to the PMBOK, this activity has the following characteristics:

Inputs Tools and Templates Outputs
project management plan, work performance reports, change requests, enterprise environmental factors, organizational process assets expert judgment, meetings, change control tools approved change requests, change log, project management plan updates, project documents updates

The perform integrated change control process is described in section 4.5 of the 5th edition of the PMBOK.

Ad blocker interference detected!


Wikia is a free-to-use site that makes money from advertising. We have a modified experience for viewers using ad blockers

Wikia is not accessible if you’ve made further modifications. Remove the custom ad blocker rule(s) and the page will load as expected.