Dependency-FF

Finish-to-finish activity dependency - activity A must be complete before activity B can be completed (from Wikipedia). A is the predecessor activity.

A predecessor is an activity that logically comes before a successor activity. The logic is usually a type of dependency. The dependancies and activity duration estimates are used to create the schedule.

Related: PERT, finish-to-finish, start-to-finish, finish-to-start, start-to-start, precedence diagramming method, start and finish times