The quality management plan is an output of the plan quality management process. The plan identifies how the quality of the project and its results will be maintained -- what processes will be used. The quality management plan is used as an input to the perform quality assurance and identify risks processes.

Related: process improvement plan, quality metrics, quality checklists

Practice QuestionEdit

See answers at the end of this article.
PMP or CAPM Exams
1. Which amongst the following would not be relevant for creating the quality management plan?

A. Checklists
B. Organizational quality policy
C. Project scope baseline
D. Schedule baseline [1]

spacers before answers

ReferencesEdit

  1. Udemy blog PMP Exam Questions: 25 Q&As for Exam Day by Brittani Sponaugle on April 3, 2014

Answers to practice questionsEdit

1. A. Checklists.

Ad blocker interference detected!


Wikia is a free-to-use site that makes money from advertising. We have a modified experience for viewers using ad blockers

Wikia is not accessible if you’ve made further modifications. Remove the custom ad blocker rule(s) and the page will load as expected.