The PMI process to sequence activities is part of the planning process group in the time management knowledge area. Once the activities have been identified and described (define activities process), this process organizes them into an order as part of the later process to develop schedule.

Related: plan schedule management, milestone

According to the PMBOK, this activity has the following characteristics:

Inputs Tools and Templates Outputs
schedule management plan, activity list, activity attributes, milestone list, project scope statement, enterprise environmental factors, organizational process assets precedence diagramming method (PDM), dependency determination, leads and lags project schedule network diagram, project documents updates

Sequence activities is described in section 6.3 of the PMBOK, 5th edition.