When analyzing the schedule, some of the things to calculate for the unfinished activities are the

early start time (ES) 
the earliest possible time for the task to begin based on the current duration estimates and dependancies
early finish time (EF) 
the earliest possible time for the task to end based on the current duration estimates and dependancies
late start time (LS) 
the latest time for the task to begin without delaying the project's end date on the current duration estimates and dependancies
late finish time (LF) 
the latest time for the task to end without delaying the project's end date on the current duration estimates and dependancies

Related: three-point estimating, network diagram, activity duration estimates, schedule network analysis, leads and lags

Ad blocker interference detected!


Wikia is a free-to-use site that makes money from advertising. We have a modified experience for viewers using ad blockers

Wikia is not accessible if you’ve made further modifications. Remove the custom ad blocker rule(s) and the page will load as expected.