Time management is one of the ten PMBOK knowledge areas. It refers to the management of the project schedule. The schedule is one of the three main constraints of project management.

Gantt2

A Gantt Chart is often used to manage and display the schedule.

Time management is described in chapter 6 of the 5th edition of the PMBOK. PMI defines the processes of project time management as

  1. Plan schedule management
  2. Define activities
  3. Sequence activities
  4. Estimate activity resources
  5. Estimate activity durations
  6. Develop schedule
  7. Control schedule

Some key documents related to time management are the schedule management plan and the schedule.

PMI's ten knowledge areas: Integration management, Scope management, Time management, Cost management, Quality management, Human resource management, Communications management, Risk management, Procurement management, Stakeholder management

Related: Gantt chart

Ad blocker interference detected!


Wikia is a free-to-use site that makes money from advertising. We have a modified experience for viewers using ad blockers

Wikia is not accessible if you’ve made further modifications. Remove the custom ad blocker rule(s) and the page will load as expected.